Meeting Minutes
Please find attached, our meeting minutes throughout the the duration of sprint 2
2022-03-13 Meeting Notes
2022-03-10 Meeting notes
2022-03-08 Meeting Notes
2022-03-07 Meeting notes
2022-03-01 Meeting notes
Standups
Please find attached, our stand ups throughout the the duration of sprint 2
Standup Sprint 2
Sprint Planning
| What product backlog items are ready and contribute toward the sprint goal? | What items will the team include on the sprint backlog? | Timeframe for each issue? | Issues that could disrupt progress to sprint goal? | What a finalised issue should look like (when “Done”) |
---|
| | Requirements | Tomorrow (3rd March) | | Updated requirements for security and performance User stories created |
MVP | End of the Week 1 (6th March) | | -Send an email by the end of the week |
Write and design our database | Second Week (8th March) | Have relevant diagrams finalised and refined |
Make our ER diagram for the database | by Friday (4th March) | | Consider connection of user, calls, email address, token, username, password API call - time called, name, user to, caller authenticated |
Design our interface, | by Friday (4th March) | | Logical reasoning for our designed intersperse - finalised methods of persistence, deployment, server API |
| | | |
Garvi | Edward | Joshua | Tay | Michelle | When2Meet- https://www.when2meet.com/?14788698-I3Akr |
---|
| Nothing coming up | | Assignment for Operating Systems 11/3/22 RIP Industry agreement making + emailing (dead) | Assignments + Weekly labs, quizzes and assignments due in the following weeks |  Confirmed meetings : 10:30am Monday (Virtual) 9pm Thursday (Virtual) 1-4pm Tuesday (In-person) |
Sprint Retrospective
Topic | What Went Well (WWW) | Even Better If (EBI) | Ways Forward |
---|
Software Design and Architecture (+ API Design) | | | |
Data Modelling | Basic design of DB kept through sprint SQLalchemy worked well for accessing DB Hosting on Heroku for Postgres worked well
| | |
Software Quality / Development of the Service | Each function is short and serves one purpose. Each function has an appropriate name which is clear about what it is meant to do With functions split over multiple functions, it is easy to group them together by what they achieve.
| | Having due dates on tickets and having meetings and at each meeting reminding everyone when things are due. Greater emapshasis and logical reasoning on Priority of each task so that members can provide help if needed
|
Deployment | Heroku deployment was easy Using environment variables for secrets was easy and secure Heroku DB integration was nice as it sends DB login straight to deployed service Was able to detect when on Heroku and only use production DB then, using sqllite database for deployment and testing.
| | |
Project Management + Communication  | Consistent updates on progress from team Good use of sprint planning - to delegate tasks Consistent meetings - when needed which included free workspace times → + group programming What went well (from Sprint 1) was well kept (refer to picture on the right) Improvement on setting clear goals and actionable for meetings From Sprint Retrospective Sprint 1 Ways Forward : “Continue same template + consistency of how often meeting minutes and stand ups occurred for iteration 2” Generally done well.
| Not everyone could always make the meetings due to unexpected plans (not noted in the sprint planning) coming up - and us moving our meeting times. Similarly from Sprint 1, greater emphasis on Asynchronous standups, for members to update the team on their progress From Sprint Retrospective Sprint 1 Ways Forward : “Create a list of questions during every meeting, that can be brought up during the physical tutor time slot” Questions weren’t brought up as often. due to Sydney weather, half the team could not attend the physical tut Many issues that had been planned during Sprint 1 ~ for Sprint 2, weren't accounted for. A lot more issues needed to be added onto Jira
| Need to re-evaluate our availabilities for Sprint 3 + 4 Use the first 5 minutes of each meeting to CLEARLY update the team in addition to updating via messages / somewhere throughout the meeting. (set aside specific time) Consistent group evaluation on the Issues created - Last minute → recognised that “emails sent to multiple recipients” didnt need to be completed, hence was removed from
|