All team members should provide their priorities, progress, and problems each day in this report.
Team name | Fudge |
---|---|
Direct supervisor | |
Table of contents |
\uD83D\uDDD3 Thursday <17/2/22>
Name | Priorities \uD83E\uDDD0 | Progress \uD83D\uDE0A | Problems \uD83D\uDE10 | |
---|---|---|---|---|
1 | See what is going on… try to get onto Jira and Confluence! | Honestly none - just had another quick skim of spec | NOTHING ABOUT OUR ACCOUNTS AND NOT MUCH MORE CLARIFICATION | |
2 | Wrap my head around the requirements of the project |
|
| |
3 | ||||
4 | ||||
5 |
\uD83D\uDDD3 Saturday <19/2/22>
Name | Priorities \uD83E\uDDD0 | Progress \uD83D\uDE0A | Problems \uD83D\uDE10 | |
---|---|---|---|---|
1 | Similar to thurs - get onto Jira/Confluence | Got our team Jira and Confluence! Went and digged around a little | Cannot do much until team is together | |
2 | Learn how Jira/Confluence works |
|
| |
3 | ||||
4 | ||||
5 |
\uD83D\uDDD3 Monday <21/2/22>
Name | Priorities \uD83E\uDDD0 | Progress \uD83D\uDE0A | Problems \uD83D\uDE10 | |
---|---|---|---|---|
1 | Sort out tasks and questions for big team meeting + tutor check-in | Sorted out team roles etc. in meeting, not much done individually | Still not sure about spec, and what we can actually do for sprint 1 | |
2 |
|
| Still not entirely sure what the requirements are and the broader context of the project | |
3 | ||||
4 | ||||
5 |
\uD83D\uDDD3 Thursday <24/2/22>
Name | Priorities \uD83E\uDDD0 | Progress \uD83D\uDE0A | Problems \uD83D\uDE10 | |
---|---|---|---|---|
1 | Finish requirements in order to do other things (interface, issues + sprint 2 planning) Ticking off marking criteria for sprint 1 | Explored Jira. Started writing requirements on tuesday, wrote more requirements since (user stories etc). Started interface document. Tabulated Architecture document. | Not sure if requirements is specific enough/meets criteria Feeling a little behind and stressed with timeline | |
2 | Get to know the spec and try to understand what is required | Allocated team roles and got to know more about how Jira and Confluence work | Not knowing the wider context of the task and trying to figure out what that means for our task. | |
3 | -Create issues on board → consider priority, tags, assign members | Initial problem with issues - disappeared, yet | ||
4 | Working on setting up Jira. Tech stack. | Worked out issues in Jira. Completed different options for tech stack. | Can’t seem to connect up github repositories. | |
5 |
\uD83D\uDDD3 Saturday <26/2/22>
Name | Priorities \uD83E\uDDD0 | Progress \uD83D\uDE0A | Problems \uD83D\uDE10 | |
---|---|---|---|---|
1 | FINISH SPRINT 1!!!! Try to get enough detail so Max will mark us well | Roadmapped with epics. Wrote some more issues with subtasks. Assigned tickets. | Not sure what to put in the planning doc, but am working on it. Also unsure of detail needed for tickets. NOT SURE IF TASKS NEED TO BE BROKEN DOWN MORE?? | |
2 | Finish the requirements for sprint 1 | Thought about the constraints of the project and potential ways to lessen the effects | Not sure on the amount of detail required for the sections | |
3 | ||||
4 | ||||
5 |
\uD83D\uDDD3 Wednesday <Date>
Name | Priorities \uD83E\uDDD0 | Progress \uD83D\uDE0A | Problems \uD83D\uDE10 | |
---|---|---|---|---|
1 | ||||
2 | ||||
3 | ||||
4 | ||||
5 |
\uD83D\uDDD3 Tuesday <Date>
Name | Priorities \uD83E\uDDD0 | Progress \uD83D\uDE0A | Problems \uD83D\uDE10 | |
---|---|---|---|---|
1 | ||||
2 | ||||
3 | ||||
4 | ||||
5 |
\uD83D\uDDD3 Monday <Date>
Name | Priorities \uD83E\uDDD0 | Progress \uD83D\uDE0A | Problems \uD83D\uDE10 | |
---|---|---|---|---|
1 | ||||
2 | ||||
3 | ||||
4 | ||||
5 |