Meeting Minutes

2022-03-10 Meeting notes

2022-03-07 Meeting notes

2022-03-01 Meeting notes

Standups

Standup Sprint 2

Sprint Planning

  • What is the goal for this sprint? Big Picture.

What product backlog items are ready and contribute toward the sprint goal?

What items will the team include on the sprint backlog?

Timeframe for each issue?

Issues that could disrupt progress to sprint goal?

What a finalised issue should look like (when “Done”)

Additional Notes

  • Get an MVP!!!

  • Try to do extra requirements (security, performance, etc.)

  • None

Requirements

Tomorrow (3rd March)

MVP

End of the Week 1 (6th March)

-Send an email by the end of the week

Write design our database

Second Week (8th March)

Make our ER diagram for the database,

by Friday (4th March)

Design our interface,

by Friday (4th March)

Write up a starter UML,

End of Week 1 (first draft) (6th March)

Garvi

Edward

Joshua

Tay

Michelle

When2Meet- https://www.when2meet.com/?14788698-I3Akr

  • No holidays will hinder capacity

  • Weekly labs, quizzes and assignments due in the next 2 weeks

Nothing coming up

  • Away for weekend (5-6/3/2022)

Assignment for Operating Systems 11/3/22 RIP

Industry agreement making + emailing (dead)

Confirmed meetings : 10:30am Monday (Virtual)

9pm Thursday (Virtual)

1-4pm Tuesday (In-person)

Sprint Retrospective

Topic

What Went Well

Even Better If

Ways Forward

Software Design and Architecture (+ API Design)

Data Modelling

Software Quality / Development of the Service

Deployment

Project Management + Communication

  • Consistent updates on progress from team

  • Good use of sprint planning - to delegate tasks

  • Consistent meetings - when needed which included free workspace times → + group programming

  • What went well (from Sprint 1 - was well kept)

  • Improvement on setting clear goals, actionable for meetings

  • Not everyone could always make the meetings

  • Great emphasis on

  • Need to re-evaluate our availabilities for Sprint 3 + 4